Intelligent Pigging On 75Km Pipeline

Intelligent Pigging On 75Km Pipeline

System Parameter
  • Diameter: 18/20" - 20" Line transitions down to 18" at A riser
  • ID Variation
  • 385mm [measured in 1.5D bend] A riser
  • 489mm max in B Launcher & riser
  • 473mm is nominal ID
  • Step change between 466m and 489mm
  • MBR
  • 20" A riser has 1.5 bends. Back to back
  • 1.5D in the 408mm [18" 19mm wt B riser
  • Miter bend at Bravo riser [design not available]
  • Line length
  • 75 km [at 0.12 m/s = 200 hours run time]
  • Wall Thicknesses
  • 20" mainline - 17.5mm
  • 20" B riser - 9.5mm / 12.5mm / 19.05mm / 21mm
  • 20" A riser - 50mm
  • 18" A riser - 19mm
  • Depth
  • 3m
Challenges

The challenges to inspect PL120 can be summarized as

  • Line is low pressure & Low flow [oil, 13.1 bar, 0.3 m/s]
  • Line is known to produce wax and difficult to clean
  • Line has complex geometry
    • 1.5 bends, back to back
    • Heavy wall
    • Short pig receiver with short minor barrel and single isolation
    • Large ID variation [385 - 489]
    • mitred bend
1920 1080 MOOR
Start Typing
Privacy Preferences

When you visit our website, it may store information through your browser from specific services, usually in the form of cookies. Here you can change your Privacy preferences. It is worth noting that blocking some types of cookies may impact your experience on our website and the services we are able to offer.

For performance and security reasons we use Cloudflare
required
Our website uses cookies, mainly from 3rd party services. Define your Privacy Preferences and/or agree to our use of cookies.